ELECTRICITY AND NATURAL GAS NETWORKS

News Electricity and natural gas networks Press release
Decision of the Supreme Administrative Court: Cross-subsidisation is in violation of unbundling regulation also in corporate restructuring

The decision issued 28 March 2024 by the Supreme Administrative Court repeals the Market Court's decision on the unbundling of Gasum’s business operations and the prohibition of cross-subvention in accordance with the requirements of the Energy Authority. The decisions of the Energy Authority will enter into force and the decision concerning penalty fee requested by the Agency will be returned to the Market Court for renewed consideration.

News Electricity and natural gas market Electricity and natural gas networks Press release 2024
Fingrid did not breach its connection and transmission obligation or the obligation to develop the grid when OL3 was connected to the grid

According to the Energy Authority’s view, the grid operator Fingrid Oyj did not breach its connection, transmission and development obligations when the Olkiluoto 3 nuclear power plant unit was connected to the electrical grid.